Spider Construction Readiness Assessment: Studi Kesiapan Proyek Pembangunan Gedung Asrama MTsN 6 Sleman
Abstract
to complete the project in the planning stage, inaccurate management, problems with materials,
labor, equipment, finance, and an unfavorable environment that hinders project implementation.
Project delays for the contractor will incur time and cost losses. For the Owner,
delays in completing project work will cause losses to the operational time of the project results.
The case study reviewed was the construction of the MTsN 6 dormitory building located in Rogoyudan,
Sinduadi, Mlati District, Sleman Regency, Yogyakarta. The idea to minimize delays in
development projects is to create a readiness assessment system in the form of a spider
construction readiness assessment, namely an assessment of aspects of administrative documents,
site location, funds and materials, implementation methods, quality and quantity of human resources,
project design, and external factors. The preparation of an assessment is based on 45 factors
that can hinder the development of a project. The results of the assessment show that the total
score obtained from all aspects is 52 out of 70. This means that construction project readiness
has a figure of 74.29%. Aspects that need to be improved in performance are aspects of design
readiness, aspects of method readiness, and aspects of external studies. The final results
of the study indicate that the Spider construction readiness assessment can be used as a way to
mprove work efficiency at the pre-construction stage.Â
Keywords: project delays, project readiness, spider construction readiness assessment
References
Alexandra and Partner Consultant.2007. Jenis-Jenis Dokumen Lelang Pengadaan.
Armani, K. A. 2012. Pengantar Manajemen Proyek. Jakarta. Universitas Guna Dharma
Ervianto, I.W. 2005. Manajemen Proyek Konstruksi Edisi Revisi. Yogyakarta.
Dipohusodo, I. 1996. Manajemen Proyek dan Konstruksi 2, Kanisius, Yogyakarta
Geller, E, Scott. 2001. The Psychology of Safety Handbook. CRC Press LLC:USA
Hafnidar A. R., 2016. Manajemen Proyek Konstruksi. Edisi 1. CV Budi Utama, Yogyakarta.
Jerome Arcaro. 2007. Pendidikan Berbasis Mutu; Prinsip-prinsip Perumusan dan Tata Langkah Penerapan. Pustaka Pelajar. Yogyakarta
Kaming, P.F.,dkk; 2000.Analisa Keterlambatan Pelaksanaan Pekerjaan pada Proyek proyek Konstruksi, Yogyakarta
Lestari, Sri, 2008, Kajian Efektivitas Model Penumbuhan Klaster Bisnis UKM Berbasis Agribisnis, Jakarta
Proboyo, B; 1998.Keterlambatan Waktu Pelaksanaan Proyek; Klasifiasi dan Peringkat dari Penyebab-penyebabnya, Universitas Kristen Petra, Surabaya
Simarga, I., Surv. Sc.1997.Pengukuran dan Pemetaan Pekerjaan Konstruksi, Pustaka Sinar Harapan, Jakarta
Soeharto, I., 1995. Manajemen Proyek Dari Konseptual Sampai Operasional.Erlangga, Jakarta.
Sugiyono. 2014. Metode Penelitian Manajemen. Bandung. Penerbit Alfabeta
Wahyudi, R dan Indra Yono, C. 2006.Pengaruh Keterlambatan Proyek terhadapPembekakan Biaya Proyek. Universitas Kristen Petra, Surabaya.
Wijayanthi, S. 2008. Faktor-faktor Penyebab Keterlambatan Waktu Pembangunan Proyek Gedung Negara di Lingkungan Pemerintah Kota Kediri, ITS
Zainal, A. 2012.Evaluasi Pembelajaran. Direktorat Jenderal Pendidikan Islam. Kementerian Agama.Jakarta